8 Fernleaf Court Build

Construction Project Report · 8 Fernleaf Court, Mount Waverley · Active · Prepared 04/08/2026
Spent
$412,300
55.7% of $740,000 budget
Cash in bank
$86,400
$14,200/week burn
Loan drawn
$330,000
61.1% of $540,000 facility
Forecast final cost
$758,500
$18,500 over budget
In briefThe project has spent $412,300 (55.7% of the $740,000 budget) over 26 weeks. On current commitments the final cost lands about $18,500 over budget. Cash of $86,400 covers roughly 6 more weeks at the current pace (to around 15/09/2026), with $210,000 of the loan facility still undrawn.
Summary
Started
03/02/2026 · target finish 18/12/2026 · 26.1 weeks elapsed
Budget
$740,000 · spent $412,300 (55.7%) · remaining $327,700
Cash in bank
$86,400
Loan drawn
$330,000 of $540,000 (61.1%)
Committed (unpaid)
$64,800 · quoted $38,200
Forecast final cost
$758,500 ($18,500 over budget) · reached around 22/12/2026
GST paid
$37,480
Weekly burn
$14,200 · runway ~6 weeks (funds run out around 15/09/2026)
Budget vs Actual
StageBudgetPaidCommittedRemaining
Site & slab$92,000$96,400—−$4,400
Frame$118,000$114,200—$3,800
Lock-up$164,000$142,600$21,500−$100
Fixing$196,000$59,100$43,300$93,600
Completion$170,000$0—$170,000
Drawdown Schedule - Planned vs Actual
StagePlanned datePlannedActual dateDrawn
Base · Eastbank28/02/2026$81,00005/03/2026$81,000
Frame · Eastbank24/04/2026$108,00029/04/2026$108,000
Lock-up · Eastbank26/06/2026$141,00010/07/2026$141,000
Fixing · Eastbank04/09/2026$113,000——
Completion · Eastbank11/12/2026$97,000——
Expenditure vs Cash vs Loan
$450k$340k$225k$110k$0 3 Feb30 Mar25 May13 Jul4 Aug ExpenditureCash in bankLoan drawn
Expenditure line draws in your accent colour in the real report. Steps in the loan line are drawdowns.
Spend by Stage
StageSpentShare
Lock-up$142,60034.6%
Frame$114,20027.7%
Site & slab$96,40023.4%
Fixing$59,10014.3%
Transactions

(Most recent of 87 transactions shown in this example - the real report lists every transaction with running balances.)

DateTypeStage / descriptionStatusAmountGSTCashLoan drawn
28/07/2026ExpenseFixing · Plaster - progress claim 2Paid−$18,700$1,700$86,400$330,000
21/07/2026ExpenseFixing · Internal doors & hardwarePaid−$9,340$849$105,100$330,000
10/07/2026Loan drawdownLock-up · EastbankPaid+$141,000—$114,440$330,000
08/07/2026ExpenseLock-up · Roofing final claimPaid−$24,200$2,200—$189,000

Figures reflect the transactions recorded at the preparation date.